Quick answer

Which form
Request for Extension, Withdrawal, or Reactivation (PDF) plus the Modify an Existing Permit web form, or do it inside AB+C if your account is assigned to the permit [2]
Due when
Permits expire 180 days after activation if the City has not performed an on-site inspection [1]. Request an extension while the permit is still Active; one extension per permit [2]
Costs what
Extension in AB+C: no fee. Extension by web form and reactivation: fee issued after you submit [2]. FY26-27 schedule line “Contractors Expired Permits”: $53.56 residential each, $82.56 commercial per discipline [5][6]
Who can ask
Owner or the assigned contractor (extension); owner, general contractor or the trade contractor listed (reactivation) [2]

If you hold a City of Austin building, electrical, mechanical or plumbing permit and the work is not finished, the date to watch is the permit’s expiration date. The City gives you two routes: extend a permit that is still Active, or reactivate one that has already expired. This guide puts the City’s own rules in one place: which route you need, which form, when, and what it costs.

180-day permit clock and the two ways out A permit is activated on day 0. If the City has not performed an on-site inspection by day 180 it expires. Before day 180 you can request one extension, or schedule a continuance of work inspection. After expiry you request reactivation. Day 0Permit paid and Active 180 days Day 180Expires with no on-site inspection Before day 180 (status Active) Request one extension per permit, or schedule a #114 Continuance of Work inspection After expiry Request reactivation (fee is invoiced after you submit) act before this date
The 180-day permit clock and the two routes. Built from the City's Activating a Permit and Modify a Permit pages.

How long a City of Austin permit lasts: the 180-day rule

The City’s permit-activation page says: “Permits will expire 180 days after activation if the City has not performed an on-site inspection (Pass or Fail).” [1] The same page points you to the Modify a Permit page to extend a permit before it expires. The City says the status should change to Active once permit fees are paid. [1]

Extend or reactivate: which one do you need?

The deciding fact is the permit’s status. Extension is for permits in an “Active” status; reactivation is for expired ones. [2]

Extend, continuance or reactivate: the three options side by side
Extend an Active permit#114 Continuance of Work inspectionReactivate an expired permit
Use whenPermit is still Active and work will run past the expiration dateStructural or other conditions do not allow inspections within the 180 daysPermit has already expired
Who can askProperty owner, or the contractor assigned to the permitNot stated on the City pageProperty owner, general contractor or trade contractor listed on the permit
LimitOne request per permitInspector decides if progress was made; if yes, expiration extends 180 daysIn-person service only for first-time reactivations, one project per day
WhereAB+C portal if your account is assigned to the permit; otherwise the Modify an Existing Permit web form with the PDF applicationSchedule a #114 Continuance of Work inspectionAB+C portal if your account is assigned to the permit; otherwise the web form with the PDF application
PDF section to mark “Yes”Section C, plus a stated reason and signaturen/aSection E
FeeNone through AB+C; through the web form a fee is issued after submissionNot stated on the City pageA fee is issued after submission

All cells are from the City’s Modify a Permit page [2] unless marked otherwise.

How to request an extension of an Active permit

  1. Check the permit is still Active. Look it up in the AB+C public permit search [9].
  2. If your AB+C account is assigned to the permit, extend it in the portal. The City says fees are not required to request an extension through the AB+C Portal. Portal steps are in the AB+C Manual [8] (search the manual for “extension”).
  3. If your account is not assigned, fill out the Request for Extension, Withdrawal, or Reactivation Application (PDF) [3], mark “Yes” in Section C, state the reason and sign it. Then open the Modify an Existing Permit web form [4], choose “Reactivate, Withdraw, or Extend” and upload the PDF with the permit number. A fee is issued after you submit.
  4. Submit once. You get an automatic confirmation email with the approximate wait time; the City asks you not to resubmit, as that creates delays.
You can request an extension only one time for each permit. [2] If conditions on the site do not allow inspections within the 180 days, the City’s alternative is a #114 Continuance of Work inspection: if the inspector finds progress, the expiration date extends 180 days. [2]

How to reactivate an expired permit

  1. Confirm who may ask. The property owner, general contractor or trade contractor listed on the permit can request reactivation. [2]
  2. Portal route: if the assigned contractor’s AB+C account is linked to the permit, reactivate it there (see the AB+C Manual [8], search “reactivate”).
  3. Web form route: complete the PDF application [3] and mark “Yes” in Section E. It must be signed by the permit holder or property owner as listed in the county appraisal district’s registry; if the property is not under an individual’s name, a certificate of formation is required to verify ownership. Upload it with the permit number on the Modify an Existing Permit web form [4].
  4. Pay the invoice. Fees for reactivation are issued after the submission. [2]

In-person service is available for first-time reactivations, one project per day, and the City asks for proof of ownership if the property is not under an individual’s name. [2]

What it costs

The City does not print one reactivation or extension price on its Modify a Permit page. It says a fee is issued after you submit a web-form extension or a reactivation, and that extension through the AB+C portal needs no fee. [2] The closest line on the current fee schedules is “Contractors Expired Permits”:

Fee schedule lines for expired permits, FY 2026-27 (effective Oct. 1, 2026)
ScheduleLine as printedAmount
Residential building plan review & permit fees [5]Contractors Expired Permits - Building, Electrical, Mechanical or Plumbing (each)$53.56
Commercial building plan review & permit fees [6]Contractors Expired Permits (per discipline) - Building, Electrical, Mechanical, Plumbing or Sign Permits$82.56

The schedules do not use the word “reactivation” for these permit types, so these are the nearest published figures, not a confirmed reactivation price. The invoice you receive is the real number. For questions about fees the City points to chat or an appointment with Building and Trade Contractor Services. [2] Paying by card in the AB+C portal adds a 2.35% service fee ($2.00 minimum); eCheck/ACH has none. [7]

Two things that surprise people

Find your own permit’s expiration date

Search the permit number in the AB+C public permit search [9] and read its status and expiration date. Write the date down with a few weeks of margin: an extension has to be requested while the permit is still Active, and each permit gets one.

This page summarizes public City of Austin pages as of the date above. Rules and fees change; confirm on the City pages in Sources before you file.

Sources

  1. Activating a Permit (Austin Development Services) — 180-day rule, “Important Tips”
  2. Modify a Permit (Austin Development Services) — extension, reactivation, who may ask, fees issued after submission
  3. Request for Extension, Withdrawal, or Reactivation Application (PDF) — the form named on the Modify a Permit page
  4. Modify an Existing Permit web form — choose “Reactivate, Withdraw, or Extend”
  5. Residential Building Plan Review & Inspection Permit Fees, FY 2026-27 (PDF) — effective 10/01/2026, “Contractors Expired Permits” line
  6. Commercial Building Plan Review & Inspection Permit Fees, FY 2026-27 (PDF) — effective 10/01/2026, “Contractors Expired Permits” line
  7. Austin Development Services fee schedules index — FY26-27 schedules; payment options and card service fee
  8. AB+C Manual — portal steps for extension and reactivation
  9. AB+C public permit search — look up a permit and its status